  Milling and Paving Schedule
|Modified: 8/17/2007|Active: NO|

Tuesday,Aug. 7             Mill west lane of Lake Street

Start milling of Parking Lot 35

 

Wednesday,Aug.8         Pave west lane of Lake Street

Finish milling Parking Lot 35

Mill Innovation Laboratory Parking Lot (west end only)

 

Thursday, Aug. 9           Pave Parking Lot 35

Open west lane and mill east lane of Lake Street

 

Friday,Aug.10                Pave east lane of Lake Street

 

Saturday,Aug.11            Open east lane of Lake Street

 

 

Notes:

-     Transformer yard work the week of Aug.6th and/or Aug.13th.

-     No trucks in two way traffic when east or west lane is closed.

-     Conflicts may occur and scheduling may change.