Proposed Time Table for Project:

ACTIVITIES AND DELIVERABLES

ACTIVITY Year 1

DELIVERABLE

TIMELINE

LINK TO OBJECTIVE (S)

Partner consultation meeting (Preparatory phase - USA) for development of exchange procedures (1st year 0-6 months)

- Develop system for transfer of credits between institutions
- Appointment of coordinators and outside advisors
- Establish baseline curriculum modules for on-line course & responsibilities
- Sign MOUs between partner institutions

On or before Month 6

1 – Consortium operations
3 – Establish Modules

Establish guidelines for each institutions’ language training and exchange procedures (1st year 0-6 months)

- Document outlining each institution’s language skills requirements, approved testing methods and other support activities for students (e.g. health, pre-departure, etc.)

On or before Month 6

1 – Consortium operations

Student recruitment and training (1st year 0-12 months)

- Each institution to develop an on-campus promotional activities including (but not limited to) speaking engagements, updating each institution’s websites, working with int’l officers on campus, etc.

On-going for the first year operations

1 – Consortium operations
2 – Recruitment Campaign

Student Exchanges initiated (2nd year)

- Deploy  initial exchange students that were recruited early in the program (1-2 per institution)
- Pre-departure counselling
- Monitor student experience and learning through quantitative and qualitative techniques
- Exit interviews upon return from exchange

2nd Year: (12 months) April 1st, 2008 – March 31st, 2009

4 – On-going monitoring
5 – Report Results

Partner consultation meeting Canada (2nd year 6-12 months)

- Review results of initial exchanges, establish best practices and modify program as necessary
- Review curriculum and adjust accordingly
- review recruitment #’s and formalize plans for year 3
- sign-off on annual report

2nd Year: (12 months) April 1st, 2008 – March 31st, 2009

1 – Consortium operations
2 – Recruitment Campaign
3 – Establish Modules
4 – On-going monitoring
5 – Report Results

Student Exchanges initiated (3rd year)

- Deploy  exchange students (3-5 per institution)
- Pre-departure counselling
- Monitor student experience and learning through quantitative and qualitative techniques
- Exit interviews upon return from exchange

3rd Year: (12 months) April 1st, 2009 – March 31st, 2010

4 – On-going monitoring
5 – Report Results

Partner consultation meeting Mexico (3rd year)

- Review results of initial exchanges, establish best practices and modify program as necessary
- Review curriculum and adjust accordingly
- review recruitment #’s and formalize plans for year 3
- sign-off on annual report

3rd Year: (12 months) April 1st, 2009 – March 31st, 2010

1 – Consortium operations
2 – Recruitment Campaign
3 – Establish Modules
4 – On-going monitoring
5 – Report Results

Student Exchanges initiated (4th year)

- Deploy  exchange students (3-5 per institution)
- Pre-departure counselling
- Monitor student experience and learning through quantitative and qualitative techniques
- Exit interviews upon return from exchange

4th Year: (12 months) April 1st, 2010 – March 31st, 2011

4 – On-going monitoring
5 – Report Results

Partner consultation meeting virtual (4th year)

- Review results of initial exchanges, establish best practices and modify program as necessary
- Review curriculum and adjust accordingly
- review recruitment #’s and formalize plans for year 3
- sign-off on annual report

4th Year: (12 months) April 1st, 2010 – March 31st, 2011

1 – Consortium operations
2 – Recruitment Campaign
3 – Establish Modules
4 – On-going monitoring
5 – Report Results

Partner consultation meeting virtual (5th year)

- Final report, comprehensive reviewing full program
- Establishment of on-going activities between consortium partners

5th Year: (6 months) April 1st, 2011 – October 2011

4 – On-going monitoring
5 – Report Results

 

 

Bureau of Business and Economic Research
College of Business and Technology
East Tennessee State University
222 Sam Wilson Hall
PO Box 70700
Johnson City, TN 37614-1710
Phone: (423) 439-5677
Fax (423) 439-8381