Projects
| SBC# |
Project Name | Description | Project Cost | Funding Source | Approved Date | Approver |
| 369/005-05-2023 | Millennium Center Chiller Replacement | This project will install a chiller(s) and all related components/work to serve the building's cooling needs and all related work. | $1,500,000 | Plant Funds (Non-Aux) | June 22, 2023 | COO |
| 369/005-01-2024 | Bosque Plaza | This project will connect the site of the new Academic Classroom (SBC# 369-005-05-2021) building with the current pedestrian way known as the "Commons" (Boulevard Commons SBC# 369/005-08-2021) creating a plaza that highlights trees surrounded by hardscape. | $2,100,000 $1,850,000 (additional funds) |
Plant Funds (Non-Aux) | February 26, 2024, March 12, 2025 |
COO |
| 369/005-02-2024 | Brinkley Center Renovation | This renovation project will be approached in two phases. This project will create collaboration and office space within the Brinkley Center. This work will consolidate faculty into this primary building of instruction space for the Department of Computing. The collaboration space will better facilitate opportunities for students and faculty to interact. This renovation may include ceilings, finishes, plumbing, HVAC, electrical, lighting, sprinkler systems, and other related work as needed. |
$2,000,000 (total)$1,000,000 (this request) |
Plant Funds (Non-Aux) | February 27, 2024 | COO |
| 369/005-03-2024 | Greenhouse Installations | Dismantle of existing greenhouse and replace with two small greenhouses. Installation of two new greenhouses on main campus. Work to include sitework, concrete work, furnishing and installation of two new greenhouses, and all associated work. |
$480,000 |
Plant Funds (Non-Aux) | March 4, 2024 | COO |
| 369/005-04-2024 | ETSU Sodexo Food Service Improvements (23-24) | Convert the "Subway" in ETSU Parking Garage to a Sodexo branded salad and sandwich shop. Work also includes conversion of the ETSU "Treehouse" sandwich shop into a convenience store. |
$990,000 |
Gift-In-Place (Contract) | April 18, 2024 | COO |
| 369/005-05-2024 | COM Bldg 2 Learning Community Renovation | Renovate the third floor of the College of Medicine (COM) Bldg. 2 to create meeting, study, and collaboration space to support the student learning communities. New layouts will require coordination of mechanical, electrical, life safety systems, and all associated work. |
$2,300,000 $2,300,000 (additional funds) |
Plant Funds (Non-Aux) |
September 13, 2024 |
COO |
| 369/005-06-2024 | Marching Band Tower | Install a fixed prefabricated structural steel observation tower approximately 40' high to be utilized by the marching band to conduct field practice. The tower will include Qty. (2) observation platforms at approximately 16' and 32' heights. |
$200,000 |
Plant Funds (Non-Aux) | September 13, 2024 | COO |
| 369/005-01-2025 | Alexander Hall Modular Classroom | Coordinate design and installation of a prefabricated modular structure with Qty.
(2) new STEM classrooms just outside Alexander Hall. The modular will meet the need for the K-12 "Univeritiy School's" programming by providing two additional classroom spaces. |
$500,000
|
Plant Funds (Non-Aux) | January 6, 2025 December 18, 2026 |
COO |
| 369/005-03-2025 | Borchuck Plaza Monument | The monument will consist of five different statues cast in bronze and set on boulders in Borchuck Plaza near Sherrod Library. This project will recognize the first African American students integrated into the student body in the late 1950s. |
$225,000 |
Plant Funds (Non-Aux) | July 28, 2025 | President |
| 369/005-04-2025 | COM Bldg 178 - Anatomy Lab Renovation | This project will renovate the existing Gross Anatomy Lab in the College of Medicine Building 178 to provide space and utilities for additional instruction stations to support the planned increased in class size. Work includes relocation of walls, doors, ceilings, mechanical modifications, and all associated work. |
$620,000 |
Plant Funds (Non-Aux) | August 29, 2025 | COO |
| 369/005-05-2025 | Buc Ridge Exterior and Structural Repairs | Perform essential repairs needed to address exterior finishes, structural repairs, and all associated work in multiple buildings at Buc Ridge Apartments. |
$2,000,000 |
Plant Funds (Aux-Housing) | September 8, 2025 | COO |
| 369/005-06-2025 | Thomas Stadium Locker Room Buildout | Buildout completion of locker rooms and office space with finishes to include lockers, lighting, plumbing fixtures, flooring, and all associated work. | $550,000 | Plant Funds (Non-Aux) | October 22, 2025 | COO |
| 369/005-01-2026 | Welcome Center Renovation | This project will create a new Welcome Center location for ETSU Admissions by renovating the current bookstore space on the first floor of the DP Culp Student Center. The bookstore space will be reworked into a smaller retail footprint to accommodate the new welcome center presentation room, welcome station, and associated offices. | $1,600,000 |
Plant Funds (Non-Aux) (A) |
December 18, 2025 | COO |
| 369/005-02-2026 | Wilson Wallis Mechatronics Renovation | Renovate to provide new space layouts with electrical, mechanical, lighting, life
safety requirements, and all associated work to support the space and equipment needs for the new Mechatronics program. New flooring, ceilings, and wall treatments will be captured. |
$625,000 |
Plant Funds (Non-Aux) (A) |
February 18, 2026 | COO |
| 369/005-03-2026 | Bristol Family Practice Renovations | Renovate 19,351 GSF at Bristol Family Practice to provide new space layouts with electrical, mechanical, lighting, life safety requirements, and all associated work to support the space and equipment needs. Work also includes renovations to create a better patient flow at the entrance and all associated work. New flooring, ceilings, and wall treatments will be captured. | $995,000 |
Plant Funds (Non-Aux) (A) |
March 2, 2026 | COO |
| 369/005-XX-2026 | COM Bldg 4 Renovation | Renovate the Medical Library first floor to support CARES clinical services and enhance student study and collaboration spaces. Work includes new layouts, finishes, furnishings, and upgrades to mechanical, electrical, lighting, and life safety systems, with minor supporting renovations as needed. | $1,750,000 |
Plant Funds (Non-Aux) (A) |
May 7, 2026 | COO |
| 369/005-XX-2026 | Lucille Clement Hall Sodexo Food Hive | Renovate approximately 1,956 GSF within Lucille Clement Hall to convert the existing Computer Lab into a combination Convenience Store/Continental Breakfast and seating area with associated food preparation, dishwashing, and storage support spaces. Work includes reconfiguration of interior layouts, modifications to mechanical, electrical, plumbing, lighting, and life safety systems, and all associated work required to support the new functions and equipment. | $990,000 |
Gift-In-Place (Contract) |
May 21, 2026 | COO |
University Commons